|
MANAGEMENT
AND ACCOUNTING WEB |

|
Cooper, R. and R. Slagmulder. 2003.
Interorganizational costing, Part 2. Cost Management
(November/December): 12-24.
Summary by Kevin Elliott
Master
of Accountancy Program
University of South Florida, Fall 2004
|
This article is the second in a two part
sequence of articles dealing with the three major aspects of interorganizational
cost management:
- improved
product design
- improved
efficiency into the manufacturing processes
- increased
efficiency of the interface between buyers and sellers
While improved product design was discussed
in the first part of this series, part two focuses on the second and third
aspects (p. 12). (See Exhibit
1 in the first article for an overall view of the ICM process).
Coordinating the product development
processes
This section of the article describes the hierarchy established by a system
of target-costing. Each firm (or tier) in the group is linked to another by the
output of a buyer’s target-costing system which becomes the input to a
supplier’s target costing system. Each tier’s allowable costs become the
basis for setting the product level costs and thereby setting the
component-level costs for the supplier (p. 12). This situation allows each
supplier to set the component-level price based on their costs of the component
purchased from their suppler. The firm at the top of the chain benefits in this
situation by being able to transmit the competitive pressure it faces down on
its suppliers. The pressure transmitted is based on the top firm’s customer
demand for quality and functionality. The firm on the end of the chain does not
have the luxury of using target costing because its suppliers are in a more
powerful position to set prices. This system becomes a valuable tool (for the
top firm) in encouraging supplier firms to become more efficient. These
relationships are illustrated in Exhibits 2 & 3
in the article. An adaptation of Exhibit 3 appears below.

These target costing chains typically range
from two to six members with most having two to four firms. The chains can be
described in one of three network setups. Each chain is either: (1) a kingdom,
where there is only one end buyer, so the end buyer and the total supplier
network are identical, (2) a barony, containing several end buyers, where the
end buyer’s supplier network will form part of the overall supplier network,
or (3) a republic, where the end-buyer’s network will form all or part of the
overall network. Chained target-costing is most effective when the buyer and
seller’s design teams can interact to change specifications in the design
stage.
The buyer-supplier
interface
The nature of the interface between the buyer and
seller is based in large part on the placement of each in the target costing
chain. There is very little power from the buyer’s end at the top of the chain
(interface A), however in the middle the buyers can have considerable influence
over suppliers (interface B), and at the end of the chain buyers can exercise
considerable power over the firm but little power over suppliers (interface C).
Therefore, those at the end are under high pressure to reduce costs with their
on suppliers.

For firms at the top and in the middle of
the target costing chain there can be significant cost reductions through
interaction with suppliers. Again the firms stuck at the end of the chain have
little no influence on supplier costs. The end firm must attempt to put pressure
on its suppliers to reduce costs, with the help of the supplier’s other
customers. Market-driven costing is most effective in the top and middle
portions of the costing chain, having little effect at the end where the firm
has little ability to control the selling price of its suppliers.
Functionality Price
Quality (FPQ) Trade-offs
Market-driven costing for firms in the middle of the chain is very simple; their
selling price is determined primarily by their buyer’s target costing systems.
These prices are set by buyers and are rarely subject to change however, the
functionality and quality of the products produced can be altered.
Functionality, quality and price make up the “Survival Triplet” and the
ability to manage it dictates the survival of firms in the middle of the chain.
These reductions can only be successful if they do not reduce the quality and
functionality of the end product (p. 16).
Interorganizational
cost investigations
A target costing chain can be limited by a buyer
designing a component that leads to manufacturing cost that are unnecessarily
high. The problem occurs when the specifications set by the buyer cause the
component to be unprofitable to the supplier, leaving the supplier with two
choices. The supplier can either refuse to produce the component or negotiate a
higher selling price (neither choice is advantageous to the supplier). However,
the supplier may turn to a third option, an interorganizational cost
investigation. An interorganizational cost investigation allows for more
fundamental changes to be made than with a simple FPQ trade-off. This type of
investigation involves the interaction of buyer and seller design teams as well
as value-engineering techniques. The greatest value is the increased scope of
the design changes that can be implemented to the end product and the component
it contains.
Interorganizational cost
investigation can reduce costs in two ways:
- The
location where activities are performed can be changed so they are performed
more efficiently.
- The
need to perform activities can be reduced or avoided by redesigning the
product and the components it contains to take full advantage of
manufacturing skills throughout the target-costing chain.

Concurrent cost management
Although interorganizational cost investigation and chained target costing
allows for a broader scope of changes to be made to an end-product and its
components these two techniques still limit the extent of the influence a buyer
can exhort. The limitation occurs because of how late in the development process
these techniques are often implemented. This limitation can be avoided by early
supplier involvement in the design process.
When a buyer allows the research and development to be outsourced for a major
function or group component, then concurrent cost management becomes a powerful
tool (p. 20). Concurrent cost management has two major approaches, parallel
and simultaneous engineering. In parallel engineering the specifications are
supplied by the supplier, in contrast to simultaneous engineering, where the
buyer’s and supplier’s design teams work together. The choice between each
is based on the benefit that interaction between the two groups would produce.
Both approaches fundamentally change supplier relations because the supplier is
not asked to design a major function or group component rather than just an
individual component. By outsourcing the R&D function the buyer has now
become dependent on the supplier for technical support and the buyer represents
a large majority of the supplier’s business.
Both parallel and simultaneous engineering provide the same benefits and have
the same flaw (p. 21):
|
Benefits |
Flaw |
- Give
suppliers more time to design their products, and hence more
opportunity to reduce costs.
- Enable
suppliers to develop new generations of their products independent of
product design process of their customers.
- Allow
faster introduction of products because the product development
processes of the buyer and supplier are occurring at the same time.
- Reduce
overall costs by allowing the supplier to spread costs over the
products of all customers.
|
- Buyers
lose much of their ability to differentiate products based on any
proprietary technology used in the major function.
|
Coordinating
manufacturing activities
Kaizen costing is the primary technique used
to coordinate manufacturing activities in a supplier network. The process begins
when a buyer transmits cost reduction pressure that it faces in the market-place
by informing suppliers that the selling price is expected to fall over time.
Kaizen cost reduction objectives differ from traditional target costing
component-specific objectives set by the buyer. The difference reflects the
basic differences between target and kaizen costing. First, savings achieved
from target costing are greater than savings from kaizen costing. Second,
cost-reduction opportunities that were not recognized during the design stage
will never be realized because once designed the components costs become fixed.
With this in mind it becomes less critical to achieve savings in a given year
since smaller costs savings can be achieved over multiple periods (p. 22).
Initiating
interorganizational kaizen costing
Initiating interorganizational kaizen
costing relies heavily on having a strong relationship with suppliers.
Interorganizational kaizen costing can be initiated by either the buyer or the
supplier. Each side must understand the mutual benefit achieved by investing in
the other. A balance of power must exist to ensure each side benefits equally
from the savings.
Buyer-led initiatives take two fundamental
approaches to reducing costs. First, educating suppliers and second giving them
access to cost savings they cannot achieve in isolation. The first approach most
often leads to redesigning a part to make it more compatible with a supplier’s
production system. The second method, allowing access to cost savings, is
archived through two methods. One method is to identify a less expensive source
for items used by the supplier (single-supplier approach) and another is to take
advantage of the buying power of the firm and its suppliers to buy in volume at
a lower rate (multiple-supplier approach). In each case the savings are passed
on to the buyer.
In supplier led initiatives, suppliers
identify new ways to design so it has a lower cost, holding quality constant.
Only through buyer interaction can this be classified as an interorganizational
kaizen costing method. Buyer involvement usually is achieved in one of three
ways:
- Buyer
changing its product in some way to accommodate the new low-cost component
- Buyer
agrees to change its production processes to accommodate changes in design
of
the component
- Buyer
provides the supplier with engineering support to help identify and
approve
changes in the design of the component or its production process
Conclusion
The three major aspects of
interorganizational cost management discussed in this paper are complimentary
and can be used to reduce costs across the supply chain. This can be achieved by
the three major enabling mechanisms that help the firms in the target-costing
chain achieve their cost reduction objectives. Interorganizational cost
investigations are a result of these mechanisms failing to achieve target costs
for one of the products. These investigations however are too late to affect the
inefficiencies that have occurred during the design of the component, clearly
defining a need for outsider help early on. Outsourcing the R&D function by
involving suppliers in the design process is one way to maximize efficiency of
operations. Finally implementing kaizen cost-reduction objectives will
continually reduce costs through continuous and gradual improvement of the
target-costing chain.
The first article in this series is as follows:
Cooper, R. and R. Slagmulder. 2003.
Interorganizational costing, Part 1. Cost Management (September/October):
14-21. (Summary).

